Project Study

Conclusion and Recommendation for Pico Hydro Project

October 15th, 2012  |  Published in Project Study

6.1    Conclusion

Pico hydro power generation is renewable energy resources build for simple operation, robust, reliable, efficient, low cost and low maintenance.

According to the results taken from our analysis, run off river in Sitio Catmon has the potential possibility to produce desire amount of electrical energy and is recommended for a pico hydro installation.  The available head and flow are quite more than enough to provide energy needs of the two consumers.  Although the river is being used for irrigation, there are decreasing occurrences of crop failures of the field due to its intensive irrigation schemes to sustain the availability of water.  It would also be possible to utilize the entire 35 1/s flow and more since it is run of river scheme in which all water will be returned to the stream and it taken during dry season.

Also, implementation of this kind of renewable energy project would be helpful to the community of Maluya  There is an opportunity for the pico hydro project to offer battery charging which could help the local community in addition to providing a small revenue steam to help pay routine maintenance of the system.  Based on the survey it seems likely that a battery financing and charging scheme could be developed the annual energy cost for off grid households.  Further surveying would need to be done to determine the exact details of the battery financing and the most appropriate rate for battery charging.

6.2    Recommendation

Before embarking on any hydro power generation project, it is essential to survey the proposed site to calculate the amount of available hydro power.  The two vital factors to consider are the flow and the head of stream or river.  The larger the flow – i.e. the more water there is, and the higher the head – i.e. the higher the distance the waterfalls the more energy is available for conversion of electricity.  Double the flow and double the power double the head the power gain.

Water turbines are generally considered as clean power producer, as the turbine causes essentially no change to the water.  They used as renewable energy source and are designed to operate for decades.  Constant maintenance and repair works will be required in this system otherwise the life of the generating equipment will be considerably reduced.  Powerhouse maintenance should be done to achieve the longer life of the turbine and other generating equipments.  The greasing of bearings should be done at least twice a month or whenever necessary because it will optimize the spin of the turbine.  The two bearings are lubricated every 3 months and lower bearing seal replaced every 6 months of continues used.

The flow of water in the river should be enough throughout a year, extreme flows can affect to the system performance and the excess flow must be controlled.  For measurement of the flow it should at least be done twice a year during the lowest season (February – May) and also in the highest season (end of September – beginning of October).  Since the installation of pico hydro power house is along the river trained technicians are required to ensure long term availability of the pico hydro and to check and controlled the excess flow of rate.

Maintenance of pico hydro is just easy and simple.  It can be done without the need for special tools.  The unit has an expected life span of 4-5 years which can be extended with regular maintenance and used of high quality bearings.
Excerpt from the Project Study for Rural Electrification by Jerome dela Cruz, Kenneth Aquino, Wilgem Regino Crespo, John Andrew Molino and Rosauro Fernando Jr of BPSU.

Tags: ,

Related Literature for Pico Hydro for Rural Electrification

September 24th, 2012  |  Published in Project Study

2.0 Related Literature

The related literature and studies help the researcher understand his topic better because it may clarify vague points about his problem. It also guides the researcher in making comparison between his findings with the findings of other similar studies.  This chapter provides a brief discussion of the Pico hydro technology available in other countries considering its impact to the society.  In relationship, our projects also cover the potential of using the Pico hydro electric generator as a source of renewable energy with consideration to the environment.

2.1 Community Pico Hydro in Sub-Saharan Africa

Site: Kathamba, Kirinyaga District, Kenya

2.1.1    Background

This scheme was installed as part of a program implemented by The Micro Hydro Centre at Nottingham Trent University to demonstrate  Pico Hydro technology in Sub Saharan Africa.  The cost of the penstock, turbine and generator equipment was met by the project funders (European Commission) and all other costs were contributed by the 65 households which the scheme now supplies with electricity.

2.1.2    Technical Summary

This case study describes a pico hydro plant using a Pelton turbine directly-coupled to an induction generator which has an electrical output of 1.1kW.  The penstock is 158m in length, 110 mm diameter PVC pipe.  The net head is 28m and the flow into the turbine is 8.4 l/s.  The electrical output of 1.1kW corresponds to a turbine generator efficiency of 48%.  The water source is a small spring with a flow rate of at least 51/s during 90% of the year ad has never been known to run completely dry.  Approximately 80m3 of storage has been provided at the intake to ensure that the turbine can be kept running for long periods.  The generator output is regulated by means of an Induction Generator Controller to ensure that the voltage and frequency are held at the correct values during conditions of changing consumer load.  Excess power is fed to a ballast load.  A 2kW cooking ring was used for this.  There are 65 households within a 550m radius of the turbine house and these are all being connected to the generator using a single-phase distribution system and insulated copper conductors.  It is possible to do this cost-effectively since the current drawn by each house is small and restricted by a current limiter so the distribution cables are also small in diameter.  Each house has a 230V supply which is sufficient for one or two energy-saving lamps and a radio.  The locations of the generator and consumer houses were recorded using a GPS system so that a distribution plan could be developed  The average cost per house for all equipment and materials was around $58 and more than 50% of this cost was contributed by the consumers.

2.1.3    General Description of the Site

Kerugoya town lies 130 km north of Nairobi on the southern foothills of Mount Kenya (Kirinyaga in Kiswahili).  Kathamba is located on the eastern side of the Mukengeria River near to Gaghihi approximately 4km north of Kerugoya  Travelling time from the town is approximately 20 minutes along unmade roads  The spring, which provides the hydraulic power for the pico hydro system, flows into the Mukengeria River approximately 300m from the source  There are 65 houses within 550m of the junction between the stream and the river and two sites for new houses.  The principle source of income in this region is through farming and the crops grown include tea, coffee, maize and fruits.

2.1.4    Community Participation

One of the principle elements which lead to the successful implementation of this project was community participation.  This was necessary both to lower the installation cost and to foster a sense of local ownership. Once it was established that there was sufficient hydro potential at this site, the first community meeting was held to discuss the project concept.  A Community Electricity Association was formed and a committee elected to manage the installation of the project and oversee the operation of the scheme.  A written agreement was subsequently signed between the community and the implementing partners.

It was agreed that all labour for the project was to be provided by the community in addition to the building materials required for the intake and the turbine house.  The consumers also were required to pay a connection fee once the turbine was commissioned.  This covered the costs of the distribution cables, housewiring and energy saving lighting bulbs.  The community association was also required to register with the local government office and to open a bank account in order to save the local contributions towards the project costs.

2.1.5    Intake and Storage Pond

The design flow for this scheme was just over 8 litres per second.  This flow will normally be available throughout most of the year although during the driest periods when it can fall to 3 l/s/  A small concrete weir was designed which would provide sufficient depth of water to ensure that the penstock is fully submerged at all times.  The natural storage area behind this weir was also enlarged by widening of the banks to 4-5 meters width and 20m length.  This provides sufficient storage to supply the extra flow required for 4 hours of evening lighting during the driest part of the year when the shortfall is at a maximum of 5.5 l/s/ 5.5  60  60 x 4 hours = 79,200 litres storage capacity required (79.2 m3).

Storage provided = 4m wide x 20m length x 1 m depth = 80m3

2.1.6    Penstock

The penstock pipe conveys water from the intake to the turbine and provides the pressure required at the nozzle.  The length required was 158 metres.  This was the shortest measured distance between the intake and the turbine.  PVC pipe with a diameter of 110mm was selected.  This gave 2m head loss with a flow of 8 l/s and provided a net head of 28m. Class B PVC (6 bar pressure rating) although a lower pressure rating could have been used if available.  The increased wall thickness however improved the reliability and lifetime of the penstock.  A trench was dug from the intake to the turbine house so that the pipe could be buried to anchor it in place and to protect it from damage by the sun.

2.1.7    Turbine house

The location for the turbine house was chosen to give the maximum available head whilst still being high enough away from the river at the bottom of the valley to avoid flooding during the rains.  The building was constructed using local stone and timber to minimize material and transportation costs.  The farmer who owned the land where powerhouse was constructed was given a free light as a concession by the local community in return for the land which was used.

2.1.8    Turbine

A Peltron turbine runner was used to convert the hydraulic power into rotating mechanical power.  This was connected directly to an induction generator and housed inside a metal casing.  The Peltron runner is defined in terms of its p.c.d. (pitch circle diameter).  Runner p.c.d.’s of 120 m, 160 mm and 200 mm were available.  Different sizes of runner operate best with different combinations of head and flow.  The runner had to rotate at the correct speed to drive the induction generator.  The speed range of these is limited because electricity at 50Hz is required for the electrical loads connected in the system.  For this site, a 6 pole generator coupled to a 200mm p.c.d. runner is suitable.  This is shown by the following equations:

The operating speed of a six pole induction generator is given by the following:

Rpm = (120 x frequency) /6 x (1 + %generator slip)

2.1.9    Local Manufacture

Turbine components were fabricated by Kenyan Electrical Distributors who received training during a 2 week course for African manufacturers of pico hydro equipment held by the Micro Hydro Centre near Nairobi in February 2001.  Another Kenyan firm, Rodson Electronics, who also participated in the training, fabricated the load controller, the enclosure and made the internal connections to the capacitors and protection equipment.

2.1.10    Generator

An IP55 1.5kW phase induction motor with 240V delta connection was selected for use as the generator.  As shown above, the required number of poles was 6.  In addition, the IP rating for the selected motor was IP55 to ensure maximum protection from entry of water and dust inside the machine.

The connection of capacitors to the motor is required in order for it to operate as a generator.  By connecting the capacitors in a C-2C arrangement it is possible to produce single-phase power efficiently from a 3-phase induction motor.

2.1.11    Operator Training

Sufficient training for key individuals was essential to ensure that the scheme will continue to be operated and maintained successfully in the future  Local electricians were involved from the beginning of the turbine and generator installation.  They were given on the job training to ensure that they could locate faults and replaced damaged components.  This was particularly important as these are the first scheme of their kind in Kenya.  The training was back up with comprehensive documentation including complete circuit diagrams and a maintenance schedule.  The new internet facility in Kerugoya town (1 hr walk from the site) provides a route to a further source of technical back-up; the operators are now able to request advice directly from pico hydro specialists in Nairobi or the UK if a problem arises which cannot be solved locally.  The consumers are charged a fixed monthly tariff depending on whether they have two lamps or one.  This is used to pay the operators wages and to contribute to a maintenance fund to replace worn components and keep the scheme operating.

2.1.12    The Distribution System

The plan below shows the position of the consumers relative to the generator.  The large circle represents a radius of 500m from the turbine house.  The location of the houses was recorded using a widely available and relatively low-cost hand-help GPS system.  This allowed the length of cable required to reach all the houses to be accurately calculated and then sized to ensure that even consumers at the furthest points in the system received a supply which was within an acceptable voltage range without excessive cost.  This was important as the entire cost of the distribution system and house wiring was met by the electricity consumers.  Local trees were used for distribution poles after basic treatment to reduce damage by termites and weathering.  The installation of the distribution system initially required a considerable degree of co-ordination to collect, treat and erect a sufficient number of poles.  Guidance was given on the required pole height, methods of treatment, and buried depth and the spacing.  Every consumer contributed one or two poles to the scheme.

The first few houses were connected under supervision from the project implementers, particularly with regard to pole positioning; cable tensioning and service were connection.  The final phase of the project, to connect the remaining houses, continued under the direction of the local electricians and committee members without the need for much external support.

The immediate prospect of electric lighting and connection of small electrical loads such as radios and, in some cases, mobile phone chargers, rapidly encouraged the payment of the remaining connection fees.  This allowed the final cables and house wiring components to be purchased.  In addition, the electricians were paid on a per consumer basis for the house wiring and therefore were keen to keep up the pace of installation of the final poles and conductors. on the right

2.1.13    Project Costs

The hydro potential at this site was limited by the small flow.  Due to the limited power available and the relatively large number of consumers living nearby, the power per house is sufficient only for one to two lamps and a radio.  This however, had the advantage that the cost of the distribution was divided amongst more people ad so households at all income levels were able to benefit.  Consumers paid for a 1 lamp or 2 lamps connection depending on how much they were able to afford.

The total cost was $58 per house.  This is particularly reasonable when compared to a lead acid battery which, when bought new, not only costs more but requires regular charging, provides DC power only and has a useful life of 2 years or less. A solar home system, providing a similar amount of power as the pico hydro has the same disadvantages as a battery only system ad would have cost at least 5 times more per house.

Excerpt from the Project Study for Rural Electrification by Jerome dela Cruz, Kenneth Aquino, Wilgem Regino Crespo, John Andrew Molino and Rosauro Fernando Jr of BPSU.

Acknowledgment Sample

September 11th, 2012  |  Published in Project Study

Acknowledgment                  

We would like to express our deepest appreciation to those people who helped even in the smallest way in making the completion of this book entitled “Pico Hydro for Rural Electrification” possible.

To our instructor Engr. Nelson S. Andres, who never failed to guide us and give important advise regarding our thesis and for any problems that was encountered regarding the completion of this book.

To our parents, for the financial support and encouragement.

To our fellow classmates, for suggestions and sharing of valuable information.

And most of all to our Almighty God, for giving us everything.  Praise be to You oh Lord God.

Thank you very much!

Jerome dela Cruz
Kenneth Aquino
Wilgem Regino Crespo
John Andrew Molino
Rosauro J. Fernando Jr.

Tags:

Parts of the Project Study

March 19th, 2011  |  Published in Project Study

Project study is used to convince the reader or audience that the project being studied is the best and most beneficial, efficient and economical in all aspects.  Of course, your project study should be based on feasibility study conducted in order to become more effective. The following are some parts of project study.

I.    Title Page
II.    Letter of Transmittal
III.    Introduction
IV.    Related Literature
V.    Methodology
VI.    Discussion of Results and Findings
VII.    Conclusion
VIII.    Recommendation
IX.    Appendix
X.    References

Other Parts

1.    Preliminaries
2.    The Problem and Its Background
3.    Review of Relate Literature and Studies
4.    Method of Study and Sources of Data
5.    Presentation, Analysis and Interpretation of Data
6.    Summary, Conclusions and Recommendatins
7.    Bibliography
8.    Appedices

Tags: ,

Acknowledgment Sample for Project Study

June 16th, 2010  |  Published in Project Study

I would have not finished this project without the support of my family who has always been there for me whenever I need them, the encouragement they give to keep me going and their love to empower me that never fails all the time. Thank you.

To my girlfriend whose support has always been my source of strength and inspiration.  To my friends who helped me in researching on different fields concerning this project.  Thank you.

I would also like to thank Engineer Desiderio V. Pepito who has given me a chance to prove that I can do things on my own.  He gave me a lot of positive perspective in life.  He who taught me things far more of my understanding.  I thank him for challenging me to do this project.  To you sir, I give you lots of thanks and respect.  Thank you.

I thank Mr. Ruben Jaraplasan, the Manufacturing Head of B-MEG Mariveles for sharing his valuable time and for giving me helpful information to finish this project.  Thank you.

And I would like to thank our Heavenly Father.  He who was and is to come; Him who is giving high hopes; for being my source of strength; for being true to what He promised me.  I praise you and I thank you my Creator and Savior.  To God be the glory.

by: Henry D. Book

Tags: ,

Statement of the Hypothesis

June 11th, 2010  |  Published in Project Study

The general hypothesis is the CompSci WebPage in the Internet will be more beneficial for future usage.  It would help a lot actually, including the ease of finding your co-alumni wherever they may be.

1.    The CompSci WebPage in the Internet is definitely better.

2.    The CompSci WebPage in the Internet is applicable to all students as subscribing in the Internet iseasy.

3.    Advantages:
a.)    Relatives of the students could see this WebPage wherever they may be without the difficulty of sending for a Yearbook.
b.)    You may produce as many copies as you want by just simply downloading from the Internet.

Disadvantages:
a.)    You need computer with Internet access to view this WebPage.
b.)    You should know the basics about the Internet, especially surfing.

4.    With this WebPage, we can say that we are not left behind in the flow of technology and we can catch up with other countries.

5.    The cost of this project may be a bit higher than the usual yearbook comparing it t a single Yearbook, but if we compare it with all the Yearbooks that have been sold per batch, it is definitely cheaper.

Excerpt from Annual Website Project by Romalyn Mamalateo, Sheryll Hipolio, Mary Jane Edquiban

Tags:

Project Name: Annual Website

June 9th, 2010  |  Published in Project Study

Chapter 1: Introduction

Have you been able to go to a party or other social gathering in the last year or two without running into conversations about the Internet? Chances are, the answer is no.

This global network has been around for nearly 20 years, but most people seems to have appeared out of nowhere in the last year or two.  In that time, more and more people have tried it out.  Many have been able to get through the initial startup, which is almost always baffling, and have come to appreciate this brave new world for the phenomenal amount of information it makes available, as well as for its entertainment value.

Today, internet is very popular. Many people and companies invest in it due to its worldwide connection and access.  It renders services such as advertisements, new technologies, and new movies especially to those popular people including celebrities and high officials, and virtually any subject you can think of.  It also serves as research reference for many, especially students.  You may even avail of chats where you can make new friends around the world.

Because of it being in demand and popular to people, as graduating students, we thought of putting a Computer Science WebPage in the Internet.

Not to boast about the graduates but to give them the advantage of being known by companies who need their services.  This is also a nice way of helping the students to be known not only in their places but also throughout the world.  Their faces will be seen as well as their scholastic records and some personal information.

As a start, we also have placed the student’s achievements and activities or organizations that he had participated in.  With this effort, we can also advertise our school and the courses we have finished.  In short, not only the students or their relatives benefits from this but also the school and those who are planning to finish a degree in the near future but haven’t decided yet what to take and where to take it.

The idea of this study started when we saw our elder brothers and sisters as well as our parents with their classical Yearbook.  We had the difficulty of scanning book pages, looking for them; they’re past activities and organizations.  With the advent of this new technology, these difficulties won’t be experienced anymore.

So why be contented with this old style of Yearbook when we can have a better and “viewer friendly” one?

Statement of the Problem

The purpose of the study is to determine whether or not a CompSci WebPage in the Internet would be feasible for future usage.

Specifically, the researcher would like to address the following problems:

  1. Is a CompSci WebPage in the Internet better than that the usual Yearbook?
  2. Will this be applicable to all students whatever their courses may be?
  3. What are its advantages as well as disadvantages?
  4. What can this project contribute to trends of technology?
  5. In terms of the cost, will the CompSci WebPage in the internet cost more than that of the classical Yearbook, and would be difference of cost worth it?

Excerpt from Annual Website Project by Romalyn Mamalateo, Sheryll Hipolio, Mary Jane Edquiban